We are monitoring the active construction of the centre for heavy engineering to keep you updated.

The erection of a metal frame for the administration and amenity building is still in progress at the site.
In K-1 building, the work on the 2A620 machine foundation reinforcement is being completed. An overhead crane with a lifting capacity of 10 tonnes has been installed. Developed by the design department, a path to move the crane in was built by the construction site workers. Simultaneously with electric ore-smelting furnace launch, cable routing is under way in K-1.
Finishing work has begun on the thermal workshop of K-2, the installation of the heating system continues.
Work on the grid connection is well underway in K-1. A base for an input switching device is being created.

The dining room is being constructed actively, including soil excavation to prepare for the construction pit and installation of a fixed formwork.