At the OKB MIKRON industrial site, construction of the TITAN machine foundation is apace in K-6 building. At the moment, concrete base for reinforcement is poured. Installation of sandwich panels has been completed in K-2, glass fixing and moulded elements are in progress.

The HEAVYCUT 5.3 machine bench has been moved to K-1 in order to be mounted on the bed frame. The bed was moved using the crane-free technology with the help of rail guides. The project of craneless lifting was developed by the design bureau of our company. The work on moving the table was carried out by the chief engineer office.

A video about moving the HEAVYCUT 5.3 machine bed using the crane-free technology is provided here.