In the Center for Modern Mechanical Engineering, construction work is in full swing. So, in the past month, the foundation of 19 grillages was poured for the fourth span of the K-6 building. The volume of the poured concrete was 338 cubic meters. m.

The construction of an administrative and amenity complex continues. The walls of the first floor are 40% ready, and 80 sq. m of paving stones.

Work on the construction of factory driveways does not stop. At the moment, 188 road slabs of the PDN-14 brand have already been laid, which ensure the strength and reliability of the roadway under heavy loads.

Also in October, a new site was organized for storing metal structures necessary for the construction of building K-6.

In the Center for Modern Mechanical Engineering, construction work is in full swing. So, in the past month, the foundation of 19 grillages was poured for the fourth span of the K-6 building. The volume of the poured concrete was 338 cubic meters. m.

The construction of an administrative and amenity complex continues. The walls of the first floor are 40% ready, and 80 sq. m of paving stones.

Work on the construction of factory driveways does not stop. At the moment, 188 road slabs of the PDN-14 brand have already been laid, which ensure the strength and reliability of the roadway under heavy loads.

Also in October, a new site was organized for storing metal structures necessary for the construction of building K-6.